Pursuant to Rule 213(a)(3) of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission, the Renewable Industries respectfully submit this Answer opposing in part the Southwest Power Pool鈥檚 January 24, 2020 Motion for Extension of Time in the above-captioned proceedings. The Renewable Industries respectfully submit that SPP has not shown good cause for such an extension. In fact, granting SPP鈥檚 motion would only serve to further delay the relief that the Commission granted in response to AWEA/APA鈥檚 Complaint,聽as an extension would perpetuate uncertainty for prospective SPP members regarding the implications for membership.